第3章试题


1. Which of the following are recognized process flow types?

A. Concurrent process flow
B. Iterative process flow
C. Linear process flow
D. Spiral process flow
E. both a and c

正确答案:E



2. The communication activity is best handled for small projects using six distinct actions (inception, elicitation, elaboration, negotiation, specification, validation).

A. True
B. False

正确答案:B



3. A good software development team always uses the same task set for every project to insure high quality work products

A. True
B. False

正确答案:B



4. Software processes can be constructed out of pre-existing software patterns to best meet the needs of a software project.

A. True
B. False

正确答案:A



5. Which of these are standards for assessing software processes?

A. SEI
B. SPICE
C. ISO 9000
D. ISO 9001
E. both b and d

正确答案:E