第34章试题


1. Software projects are inevitably late and there is nothing that can explain why.

A. True
B. False

正确答案:B



2. It is unethical to undertake a project that you know in advance cannot be completed by the customer's deadline, unless you inform the customer of the risk and establish a project plan that can deliver the needed system incrementally.

A. True
B. False

正确答案:A



3. Which of the following is not one of the guiding principles of software project scheduling:

A. compartmentalization
B. market assessment
C. time allocation
D. effort validation

正确答案:B



4. Doubling the size of your software project team is guaranteed to cut project completion time in half.

A. True
B. False

正确答案:B



5. The software equation can be used to show that by extending the project deadline slightly

A. fewer people are required
B. you are guaranteed to meet the deadline
C. more lines of code can be produced
D. none of the above

正确答案:A



6. The 40-20-40 rule suggests that the least of amount of development effort be spent on

A. estimation and planning
B. analysis and design
C. coding
D. testing

正确答案:C



7. A task set is a collection of

A. engineering work tasks, milestones, deliverables
B. task assignments, cost estimates, metrics
C. milestones, deliverables, metrics
D. responsibilities, milestones, documents

正确答案:A



8. The task (activity) network is a useful mechanism for

A. computing the overall effort estimate
B. detecting intertask dependencies
C. determining the critical path
D. specifying the task set to the customer
E. b and c

正确答案:E



9. Tasks that lie on the critical path in a task network may be completed in any order as long as the project is on schedule.

A. True
B. False

正确答案:B



10. Two tools for computing critical path and project completion times from activity networks are

A. CPM
B. DRE
C. FP
D. PERT
E. a and d

正确答案:E



11. Timeline charts assist project managers in determining what tasks will be conducted at a given point in time.

A. True
B. False

正确答案:A



12. The best indicator of progress on a software project is the completion

A. of a defined engineering activity task
B. of a successful budget review meeting on time
C. and successful review of a defined software work product
D. and successful acceptance of project prototype by the customer

正确答案:C



13. Since iterative process model work best for object-oriented projects it is impossible to determine whether an increment will be completed on time or not.

A. True
B. False

正确答案:B



14. WebApp projects only require the creation of a macro schedule.

A. True
B. False

正确答案:B



15. The purpose of earned value analysis is to

A. determine how to compensate developers based on their productivity
B. provide a quantitative means of assessing software project progress
C. provide a qualitative means of assessing software project progress
D. set the price point for a software product based on development effort

正确答案:B



16. Earned value analysis is a technique that allows managers to take corrective action before a project crisis develops.

A. True
B. False

正确答案:A