第35章试题
1. Proactive risk management is sometimes described as fire fighting.
A. TrueB. False
正确答案:B
2. Software risk always involves two characteristics
A. fire fighting and crisis managementB. known and unknown risks
C. uncertainty and loss
D. staffing and budget
正确答案:C
3. Three categories of risks are
A. business risks, personnel risks, budget risksB. project risks, technical risks, business risks
C. planning risks, technical risks, personnel risks
D. management risks, technical risks, design risks
正确答案:B
4. Generic risks require far more attention than product-specific risks.
A. TrueB. False
正确答案:B
5. A risk item checklist would contain known and predictable risks from which of these categories?
A. product sizeB. development environment
C. staff size
D. process definition
E. all of the above
正确答案:E
6. Questions that should be asked to assess the overall project risk include:
A. Have top managers formally committed to support the project?B. Are end-users committed to the project and proposed system being built?
C. Are requirement fully understood by development team and customers?
D. Does the proposed budget have time allocated for marketing?
E. a, b, c
正确答案:E
7. Software risk impact assessment should focus on consequences affecting
A. planning, resources, cost, scheduleB. marketability, cost, personnel
C. business, technology, process
D. performance, support, cost, schedule
正确答案:D
8. Risk projection attempts to rate each risk in two ways
A. likelihood and costB. likelihood and impact
C. likelihood and consequences
D. likelihood and exposure
正确答案:C
9. Risk tables are sorted by
A. probability and costB. probability and impact
C. probability and consequences
D. probability and exposure
正确答案:B
10. Individual team members can make their own estimate for a risk probability and then develop a consensus value.
A. TrueB. False
正确答案:A
11. Which factors affect the probable consequences likely if a risk does occur?
A. risk costB. risk timing
C. risk scope
D. risk resources
E. b and c
正确答案:E
12. The reason for refining risks is to break them into smaller units having different consequences.
A. TrueB. False
正确答案:B
13. Effective risk management plan needs to address which of these issues?
A. risk avoidanceB. risk monitoring
C. contingency planning
D. all of the above
正确答案:D
14. Risk monitoring involves watching the risk indicators defined for the project and not determining the effectiveness of the risk mitigation steps themselves.
A. TrueB. False
正确答案:B
15. Hazard analysis focuses on the identification and assessment of potential hazards that can cause
A. project terminationB. schedule slippage
C. cost overruns
D. an entire system to fail
正确答案:D
16. Risk information sheets (RIS) are never an acceptable substitute for a full risk mitigation, monitoring, and management (RMMM) plan.
A. TrueB. False
正确答案:B